Belmont Village

Phase 1 Environmental Abatement – Completed 11/2/16

Phase 2 Building Demolition – Approximate Duration: November 2016 – February 2017

  • Sidewalk and parking lanes have been closed and will remain closed for the duration of the project
  • ComEd Scheduled to disconnect and reconfigure power at alley 11/7 & 11/8
  • Perimeter scaffolding and scrim to continue throughout November
  • Interior demolition November
  • Structural demolition December thru February

Thank you for your continued patience and understanding as we work to safely and efficiently prepare the property for new construction. Should you have questions or would like additional information, please contact the Belmont Village Community Liaison or Construction Logistics Liaison.