Belmont Village

Phase 2 Building Demolition – Approximate Duration: November 2016 – February 2017

  • Sidewalk and parking lanes have been closed and will remain closed for the duration of the project
  • Perimeter scaffolding and scrim is starting to be removed from the top of the building as structural demolition progresses
  • Interior strip out continues on floors 1 – 5
  • Structural demolition December through February

Thank you for your continued patience and understanding as we work to safely and efficiently prepare the property for new construction. Should you have questions or would like additional information, please contact the Belmont Village Community Liaison or Construction Logistics Liaison.