Belmont Village

Belmont Village Phase 2 Building Demolition – Completion – February 2017

  • Sidewalk and parking lanes have been closed and will remain closed for the duration of the project.
  • The building is currently demolished down to the 4th floor.
  • Perimeter scaffolding and scrim will continue to be removed from the top of the building as structural demolition progresses.
  • Interior strip out demolition has been completed.
  • Structural demolition targeting completion on schedule in February.
  • See progress photos below.