Schedule, Work Notice

Phase 1 – Complete

  • Temporary construction fence and wind screen are in place and will remain for the duration of the project.

Phase 2 Complete

  • The sidewalk on Orchard will be re-opened at the end of November.
  • Temporary construction fence and wind screen are in place and will remain for the duration of the project.

Phase 3 – In progress – Scheduled to be completed in January of 2017

  • The pedestrian canopy on Fullerton will remain in place until December.
  • Structural demolition will continue.

Phase 4 – Complete

  • The pedestrian canopy on Fullerton will remain in place until December.
  • Structural demolition will continue.

Phase 5 – In progress – Scheduled to be completed in December of 2016

  • The pedestrian canopy on Fullerton and Lincoln is being installed the week of 11/7.
  • Structural demolition will start the week of 11/7.
  • Click to see drawing.

Phase 2 , 3 and 4 – Foundation removal scheduled to be conducted November – February

  • Removal of existing foundations.

D1 & D2 building demolition – Scheduled to be completed in November