Schedule, Work Notice

All buildings are now down to grade level and what remains for demolition is the first floor slabs and basement columns and slabs. The demolition phase of the project is about 75% complete at this point. (See the below photo taken Thursday, December 8.)

A few updates:

  • The decision has been made to remove the below grade MRI suite that is under the Orchard sidewalk. This will require closure of the sidewalk beginning next week and closure of the parking lane on the West side of Orchard for 4-6 weeks. See the logistics plan for the Orchard sidewalk closure HERE.
  • The remaining pedestrian canopy that is on Lincoln and Fullerton will be removed by the end of December.