We are in our final phase of demolition! Click to see Phase 6 plans.

  • All that remains to complete the demolition phase is the removal of all basement foundation. We are currently approximately  60% complete with the removal of existing foundations and estimate completion within the next five weeks.
  • The sidewalk closure on the West side of Orchard, South of Kemper, was removed and the sidewalk was re-opened on 1/5/17.
  • We plan on removing the remaining pedestrian canopies located on Lincoln and Fullerton the week of 1/16/17.