In conjunction with the future work at the former Children’s Memorial Hospital, a contractor will be conducting soil boring work starting as early as Thursday, March 31 and extending through Wednesday, April 13 between the hours of 8:00 AM and 5:00 PM. The approximate work areas are shown as shaded red on the picture below.

Access to the sidewalk and parking spots adjacent to these areas may be restricted for 1 to 2 days at each work area as work progresses.

The work will not affect access to the sidewalk or parking outside of the working hours of Monday through Friday, 8 AM to 5 PM.

The drilling equipment will consist of a drill rig and support trucks. Two to three vehicles, inclusive of the drill rig, are anticipated at each work area. The noise generated during drilling typically consists of large truck noise with intermittent periods of steel-on-steel hammer sounds.

 

The approximate work area schedule is below. This schedule is subject to change.